1. The Deepwater
Horizon disaster occurred due to multiple reasons. The primary three that are
suspected are due to the failure were the well casing, number of centralizers
used, and decision not to perform a cement bong log. Although those are
considered main contributors, there were failures seen from every level;
starting at the individual level and all through the industry as seen below.
Individual
|
Team
|
Corporate
|
Industry
|
Disabled the emergency gas alarms so that people could sleep at night
|
Under budget estimations of
initial costs
|
Performance oriented vs
safety oriented
|
Audit found 390 failures on
rig but did not hold BP accountable
|
11 different companies used to construct
casing
|
Lack of safety in 18 core values
|
Did not establish set safety regulations that
called for constant status updates
|
|
Did not check integrity of
cement
|
Too cost conscious
|
||
Numerous signatures needed to make change
|
2.
The lack of BP leaders to side on caution was a
common theme that lead to the Deepwater Horizon disaster. They originally under
budgeted the project and therefore all of the time and money for safety was
disregarded in order to make up for the immediate loss. They used the cheaper
and less safe casing, did not repair the 390 failed components from an audit,
and ignored science which proved the cement cap to be misaligned due to the
extra money for repairs. The executives also did not have experience to start
the project. The most tenured executive was three months. This lead to rash
decisions to ignore the more expensive safety precautions for the need of
immediate results. The industry also lead to the failure. There was an audit
done in which they found 390 failures on the brig that needed immediate
repairs. The auditors did not follow-up and did not hold BP accountable. The
rig was never turned off and the repairs were never completed.
3.
The ability to voice opinions were weak and inefficient.
The ethical values were there and the science backed their concerns, but they
did not voice their opinions appropriately. There were long e-mail chains
between the individuals with concerns and BP executives. This is inefficient as
e-mails may be interpreted incorrectly, such as targeting the executives. It
also does not allow the individual to have the emotional impact as an in person
meeting would. BP also used a decision tree that only they created. This means
that there could have been vital decisions in the tree that were missing, but
with only one group creating it, there was no input. Once the tree was reviewed
in court it was proven that there could have been other cement capping safety
options included in the tree.
4.
Linear casing involves hanging a steel tube from
a liner hanger with a tube already in the well than inserting another tube on
top of the prior one. This provides 4 barriers of protection against leaks.
Long string casing involves a single string of steel casing from the seafloor
to the bottom of the well. This provides 2 barriers and does take less time to
install.
The main argument between the two was safety versus money and time.
Linear casing is safer but will take more time to complete and will cost more
money. Since BP was already behind schedule and running a much larger deficit
than planned, they bypassed the safety for the long string casing. The
estimated time saved was three days and the savings in cost was estimated to be
approximately $7-$10 million. In the overall holistic viewpoint, this is a very
small amount. BP was already spending over $500 million per day on the
construction so the $7-$10 million in savings is minor.
5.
From this analysis, BP and the industry had
ineffective organization. It originally took about eleven executive signatures
to get any new process approved. This long process would drag out any safety
decision. The short tenure of the executives in charge of the project lead them
to be nearsighted. They looked at short term set-up costs and deficits versus
the long-term gains from the additional safety investments. The industry also
failed by not holding BP accountable for their failed audits. They also did not
screen any of the project during the life the project.
6.
The Deepwater Horizon disaster could have been
mitigated if they aired on the side of caution. The simulations and science
behind the cement not being flush was ignored which caused the explosion. BP
executives ignored the warnings because it would cost more time to repair the
current issue. They also decided to save three days by choosing long string
casing over linear casing. These unethical decisions can be traced to BP’s
organizational structure. They were focused on results and product versus
safety. In fact, of their 16 core business values, not a single one had to deal
directly with safety. Also, each project was run by different executives who
often competed with each other. This resulted in executives often not sharing
best practices with each other.
7.
The BP executives, focused on cost reduction and
performance, often dismissed safety regards. They called the cement bong log
test not a quantifiable test and the need for it was not necessary in practical
use. The rash decisions can be traced to multiple issues with the project. The
project with under budgeted which resulted in immediate deficits. This put
pressure on the new executives to cut costs to mitigate their immediate losses.
This then caused them to be more close minded and only considering factors that
were cheaper and faster without thinking of the long-term implications. The arguments
for safety were also ineffective. They involved e-mails chains and targeted the
executives and their decision making abilities. They should have conducted in
person meetings to show that they are focusing on the long-term safety of the
product.
8.
As the CEO we would have viewed both sides of
the arguments and though of the situation as a long-term investment. The
initial upfront cost are easily justifiable over a long-term life of the rig.
We would also analyze worst case scenarios if we chose either safety or the
cheaper solutions. Having a risk management team to analyze both may have
produced the environmental scenarios which actually occurred. Short-term the
culture needs to include safety in their core values. Changing that immediately
will start the long-term shift towards a safety driven company. We would also
not make each rig run by individual executives. There needs to be conferences
and meetings were the executives can share best practices. Instead of competing
with one another, they need to work to continue to grow the overall BP brand.
There also needs to be an increased risk management team. When they present
their findings, it needs to be in a personal meeting. E-mail chains and phone
calls are not proper ways to exhibit such critical information.
To
make these changes stick, as a CEO, we would have strict guidelines to hold
other accountable. We would continually travel to different rigs to have random
inspections and attend these conferences to ensure that the best practices were
being shared. Also, with changing the core values to focus on safety, we would
only hire and promote others who share the safety values that BP needs.
No comments:
Post a Comment